Technical inspection, development of technical specifications and tender documents for the construction of thermal power plants, the refinery of Aden, Republic of Yemen.

Customer: Aden Oil Refinery Company

 

Steps:

1. survey of the development, preparation of specifications
2. The preparation of the tender for the construction of thermal power plants.

Implementation:

1. A comprehensive assessment of the suitability of the proposed site for development and resource requirements, the evaluation circuitry for communications and future infrastructure (including equipment), the development of technical requirements for the construction of the power plant have been conducted.
2. Tender documentation has been prepared.
3. Criteria for evaluation of bids for potential partners have been developed.

Group members: "TatNIPIenergoprom", Engineering Centre Energoprogress , "KER-Avtomatika", "KER-Naladka"