ACS of gas turbine plant with a capacity of 50 MW at Kazan TPS-1 (JSC "Generation Company")

APCS of gas turbine power plant is designed to manage all elements of a gas turbine plant: a gas turbine engine, recovery boiler, booster gas compressor and electrical part of the gas turbine power plant.

Gas turbine power plant is equipped with control and monitoring system based on DCS «Ovation» (Emerson).

Result:

  • autoregulation of process parameters with specified characteristics;
  • Management control of fuel gas turbine engine;
  • functional group control (start of gas turbine engine with the inclusion in the network).
Group members: "TatNIPIenergoprom", Engineering Centre Energoprogress , "KER-Avtomatika", "KER-Naladka"